Site Clearance for Wells, Platforms, and Other Facilities

§250.1740 — How must I verify that the site of a permanently plugged well, removed platform, or other removed facility is clear of obstructions?

Within 60 days after you permanently plug a well or remove a platform or other facility, you must verify that the site is clear of obstructions by using one of the following methods:

 
(a)
For a well site, you must either:
 
(1)
Drag a trawl over the site;
 
(2)
Scan across the location using sonar equipment;
 
(3)
Inspect the site using a diver;
 
(4)
Videotape the site using a camera on a remotely operated vehicle (ROV); or
 
(5)
Use another method approved by the District Manager if the particular site conditions warrant.
 
(b)
For a platform or other facility site in water depths less than 300 feet, you must drag a trawl over the site.
 
(c)
For a platform or other facility site in water depths 300 feet or more, you must either:
 
(1)
Drag a trawl over the site;
 
(2)
Scan across the site using sonar equipment; or
 
(3)
Use another method approved by the Regional Supervisor if the particular site conditions warrant.

   Reason: