§250.1726 — When must I submit an initial platform removal application and what must it include?

An initial platform removal application is required only for leases and pipeline rights-of-way in the Pacific OCS Region or the Alaska OCS Region. It must include the following information:

 
(a)
Platform or other facility removal procedures, including the types of vessels and equipment you will use;
 
(b)
Facilities (including pipelines) you plan to remove or leave in place;
 
(c)
Platform or other facility transportation and disposal plans;
 
(d)
Plans to protect marine life and the environment during decommissioning operations, including a brief assessment of the environmental impacts of the operations, and procedures and mitigation measures that you will take to minimize the impacts; and
 
(e)
A projected decommissioning schedule.