§192.711 — Transmission lines: General requirements for repair procedures
 
(a)
Temporary repairs. Each operator must take immediate temporary measures to protect the public whenever:
 
(1)
A leak, imperfection, or damage that impairs its serviceability is found in a segment of steel transmission line operating at or above 40 percent of the SMYS; and
 
(2)
It is not feasible to make a permanent repair at the time of discovery.
 
(b)
Permanent repairs. An operator must make permanent repairs on its pipeline system according to the following:
 
(1)
Non integrity management repairs: The operator must make permanent repairs as soon as feasible.
 
(2)
Integrity management repairs: When an operator discovers a condition on a pipeline covered under Subpart O-Gas Transmission Pipeline Integrity Management, the operator must remediate the condition as prescribed by §192.933(d).
 
(c)
Welded patch. Except as provided in §192.717(b)(3), no operator may use a welded patch as a means of repair.

[Amdt. 192-114, 75 FR 48604, Aug. 11, 2010]

   Reason: